Existing On-Going Projects:
1. Ammonia Plant revamp:
At present, Company is producing about 1,950 MTPD Ammonia from both fuel oil and natural gas route after installation of S-300 revamp. It is planned to increase the Ammonia production capacity from 1,950 MTPD to 2,100 MTPD by installation of Ammonia Make-up Gas Convertor Loop [AMUGL], in existing Ammonia Synthesis Loop (ASL). The Project will also increase the reliability of existing ASL.
This will increase Ammonia production by 50,000 MT per annum. Agreement has been signed with M/s. Topsoe, Denmark, the Technology Licensor for providing Basic Engineering Package (BEP) & supply of proprietary equipment & commissioning assistance.
Project shall be executed on EPC basis and is likely to be completed by Second quarter of the FY 2027-28.
2. Coal based Captive Co-Generation Power Plant (CCPP) at Dahej:
The Company has set up 100 MT/Hr capacity gas based Boiler at TDI – II Dahej Complex to meet captive steam requirement, while power is being sourced from DGVCL Grid. There is large variation in gas prices.
The Board of Directors has approved the implementation of coal based Captive Generation Power Plant (CCPP) Project having a capacity to produce 18 MW Power and 150 MT/ Hr. Steam in October 2022, in order to reduce cost of steam and power and to improve reliability of TDI-II Dahej Plant. LSTK Contract has been awarded to M/s. Thyssenkrupp Industries India Private Limited in October 2022.
Engineering, Procurement and Construction activities are progressing and Power Project is expected to be completed by November 2026.
The Board of Directors has approved the implementation of WNA-III Plant having a capacity of 600 MTPD in August 2024.
LEPC Contract has been awarded to M/s. Thyssenkrupp UHDE India Pvt. Ltd. (tkUIPL) in September 2024.
Engineering, Procurement and Construction activities are progressing and Project is expected to be completed by June 2027.
4. Ammonium Nitrate-II (AN-II) Project:
The Board of Directors have already approved the implementation of AN-II project having capacity of 480 MTPD in November 2025.
EPC Contract has been awarded to M/s. Toyo Engineering India Pvt. Ltd in December 2025.
Engineering, Procurement and Construction activities are progressing and Project is expected to be completed by August 2027.
NEW UPCOMING PROJECTS:
1. New CFBC Boiler:
Your Company is planning to install New CFBC boiler having capacity of 180~200 MT/hr in view of replacement of existing old coal fired Boilers. Board has approved the project on February 10, 2026. Pre-project activity is under progress.
2. New four power lines of 132 KV:
Your Company is planning to install four power lines of 132 KV to improve reliability of GETCO Power supply for GNFC complex, Bharuch site. Board has approved the project on February 10, 2026. Pre-project activity is under progress.