FINANCIAL STATEMENTS
CONSOLIDATED
NOTES TO THE CONSOLIDATED FINANCIAL STATEMENTS FOR THE YEAR ENDED MARCH 31, 2026
To be completed in 1 to 2 year
2 to 3 year more than 3 years
As on 31.03.2025 - Projects and Schemes in Progress - Urea Reactor replacement - Installation of H2 Compressor at ASGP plant - Liaison Office Renovation - New Delhi - Rock phosphate 2A silo height increase - New CMG Office Building - Fire fighting system for GNFC Township - Installation of Buffer tank EA plant - Filled Carbouy platform construction - Dedicated fibre-optic network - Construction of mechanical workshop for Dry sectin - Additional MTD storage tanks * - Fire water pump house upgradation S-500869 - DM water filling & Drainage System upgradation - Other Various Modification / Upgradation schemes Total as on 31.03.2025
11.05 * None of the projects has exceeded it's cost compared to its original plan except Additional MTD storage tanks which is exceeded by 0.47 crore.